Skip to content
Horizontal-logo
  • 125 Years of Exceptional
  • Markets
    • Aviation
    • Cultural Resources
    • Education
    • Federal
    • Food & Beverage
    • Justice
    • Renewable Energy
    • State & Local
    • Transportation
    • Water
  • Services
    • Architecture & Interiors
    • Commissioning
    • Construction Services
    • Engineering
    • Environmental
    • Fabrication & Custom Manufacturing
    • Planning
    • Sustainability & Resilience
    • Technology & Security
  • Portfolio
  • News
  • About
    • Purpose & Values
    • Meet Our Team
    • Inclusion & Belonging
    • Corporate Responsibility
    • Locations
    • Scholarship Opportunities
    • Our History
    • Events
  • Careers
  • 125 Years of Exceptional
  • Markets
    • Aviation
    • Cultural Resources
    • Education
    • Federal
    • Food & Beverage
    • Justice
    • Renewable Energy
    • State & Local
    • Transportation
    • Water
  • Services
    • Architecture & Interiors
    • Commissioning
    • Construction Services
    • Engineering
    • Environmental
    • Fabrication & Custom Manufacturing
    • Planning
    • Sustainability & Resilience
    • Technology & Security
  • Portfolio
  • News
  • About
    • Purpose & Values
    • Meet Our Team
    • Inclusion & Belonging
    • Corporate Responsibility
    • Locations
    • Scholarship Opportunities
    • Our History
    • Events
  • Careers

Cost-Effective Approaches for Substructure Rehabilitation

  • August 12, 2021
Cap and column and T-type pier bridge components

For superstructure replacement projects, rehabilitating the existing substructure instead of replacing the bridge itself is often a great challenge. However, with the reduced transportation funding pushing many DOTs to preservation mode rather than complete replacement, rehabilitation of structures is needed to keep the traffic moving safely on new and existing structures.

While rehabilitating four interstate ramps in Dayton, Ohio, for the Ohio Department of Transportation, District 7, we discovered that replacing the superstructure on MOT-35-1516N, a 12-span, curved ramp over CSX and Norfolk Southern Railroads with no hinges, would add too much stress to the existing substructure to meet Association of State Highway and Transportation Officials (AASHTO) Standard Specifications. By using an innovative approach to rehabilitate the substructure, we ultimately saved the owners over $2 million. Throughout this project and many others, our team has learned many valuable lessons that have aided us in providing effective solutions. Here I provide a case study to help you determine if rehabilitating your substructure is a viable alternative for your bridge project.

Replacing the existing superstructure

The Y-geometry of the ramps, locations of the drop beams, and the ramp closure restriction all factored into the decision to replace the superstructure on MOT-35-1516N. This also allowed us to improve the joint condition by relocating them to the piers. Due to how much the loading and geometry of the piers would change, we evaluated the substructure capacity for the proposed loading, including thermal forces due to elastomeric bearings and an additional beam line for unit 3 for maintenance of traffic.

Interstate bridge ramp substructure rehabilitation
Bridge MOT-35-1516N over CSX & NS Railroads

Analyzing the existing cap and column and T-type Piers

Using analysis software, we reviewed the impacts the superstructure replacement would have on the substructure. Most components of the cap and column piers (Piers 8, 9, 10 & 11) would remain unaffected, but several key areas on the cap and column piers would be impacted.

  • The pier cap shear capacity would be 33-46% over.
  • The bearing capacity on piers 8 and 11 would be 5% over.

For the T-type piers (Piers 2-6, 7N, 7S, 12, 13), the pier cap shear and moment capacities were adequate. Majority of stem and some footing of T-type piers would be impacted.

  • The pier stem moment capacity would be 25-150% over.
  • The flexural capacity of footing for pier 7N would be 90% over and piers 7S would be 36% over.
  • Maximum overstress on the bearing capacity of T-type pier footings would be less than 10%.

We either needed to fully replace the bridge or come up with an innovative approach to rehabilitating the substructure. To minimize schedule and cost impacts, rehabilitation of overstressed substructure components was chosen in lieu of substructure replacement.

Rehabilitating the cap and column pier caps and T-type piers

Our team explored multiple options to improve the shear capacity on the cap and column pier caps. These included fiber wrapping the pier caps or designing a concrete encasement for them. We ultimately decided on concrete encasement as this increased the shear capacity through composite action and would make inspection easier, compared to fiber wrapping them.

Cap and column pier caps on MOT-75 interstate bridge during construction
Rehabilitation of cap & column pier caps

 

cap and column pier cap elevation view
Cap & column pier cap elevation view with concrete encasement and dowels

 

cap and column pier cap tip and side views
Cap & column pier cap rehabilitation – top and side views

Concrete encasement with vertical reinforcing steel was also used to improve the T-type pier stem wall’s flexural capacity. The vertical reinforcing steel was doweled into the footing to develop the flexural reinforcement.

Diagram of T-type pier stem section
T-type pier stem section view with concrete encasement and dowels into existing wall and vertical steel
T-type pier column rehabilitation
Rehabilitation of T-type pier columns

Concrete topping with vertical steel dowels to develop composite action with the existing footing was used to improve the flexural capacity of overstressed T-type pier footings.

T-type pier footing
T-type pier footing elevation view with footing vertical extension and dowels into existing footing

Coordination and stakeholder involvement

There were multiple factors that required coordination with various stakeholders to complete the project successfully. In addition to limiting the project construction costs, the goal was to construct the project per the original schedule with minimal disruption to travelers. We developed a complex Maintenance of Traffic Alternatives Analysis to stage construction alongside other ongoing projects in the area to limit impacts to the public.

Since MOT-35-1516N bridge ran over two railroads, their involvement both early on and throughout the process was paramount. Through our team’s extensive experience designing structures over railroads, we have gained valuable lessons that can be widely applied. When designing structures over railroads, some critical considerations include:

  • CSX & NS require flaggers within 30 feet of the tracks so consider working within 25 feet.
  • When excavating near a railroad, it is good to provide a cross section with sheeting/open cut limits detailed.
  • Consider placement of equipment and thickness of shoring in your design.
  • It is highly risky to assume existing foundation limits were built precisely per the plans.
  • Reconfirm railroad concurrence prior to selling the project and again at pre-construction.

In the end, our team was able to meet ODOT’s goals of delivering a quality, cost-effective, practical and safe project that their travelers will enjoy for years to come.

KV Balasubramanyam headshot

Dr. K.V. (Bala) Balasubramanyam, PE

Dr. K.V. (Bala) Balasubramanyam is Mead & Hunt’s National Bridge Design Practice Leader, Principal, and a Vice President serving the Transportation sector out of our Columbus, Ohio office. He has decades of experience in bridge inspection, design, and detailing, encompassing nearly all types of prestressed concrete, steel and reinforced concrete bridges. Outside of work, Bala is a college football and cricket fan and watches them regularly; spends time with family watching Hindi, Tamil & Hollywood movies; and plays card games such as poker, Indian and Gin Rummy.

Linkedin Envelope Readme
PrevPrevious
NextNext

Most Popular

Nicki Combs Named President-Elect of ACRA
September 10, 2025
A Glimpse into History: Why Jelly Juice Jars Were Found in Virginia Schoolhouses
August 26, 2025
Transportation Impact Fees: How Developer Contributions Support Healthier Communities
August 20, 2025
80 Years of Planning and Building Our Nation’s Military Aviation
August 19, 2025

Main Menu

  • Home
  • Markets
  • Services
  • Portfolio
  • News
  • About
  • Careers
  • Home
  • Markets
  • Services
  • Portfolio
  • News
  • About
  • Careers

Useful Links

  • Ebids
  • Corporate Responsibility
  • Equipment & Parts
  • GSA Schedules Program
  • Government Contract Vehicles
  • Policy for Third-Party Recruiters
  • Transparency in Coverage
  • Ebids
  • Corporate Responsibility
  • Equipment & Parts
  • GSA Schedules Program
  • Government Contract Vehicles
  • Policy for Third-Party Recruiters
  • Transparency in Coverage

Get in touch

  • Apply Today
  • Contact Us
  • Locations
  • Title VI
  • Apply Today
  • Contact Us
  • Locations
  • Title VI

Connect with us

Linkedin Facebook Instagram Vimeo

© 2025 Mead & Hunt, Inc. All rights reserved.

[uc-privacysettings] | Privacy & CCPA Policy | Do Not Sell | Site Map
This website uses cookies to improve your experience. Read full privacy policy
ACCEPTREJECTSETTINGS
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Functional
Functional cookies help to perform certain functionalities like sharing the content of the website on social media platforms, collect feedbacks, and other third-party features.
Performance
Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Analytics
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics the number of visitors, bounce rate, traffic source, etc.
Advertisement
Advertisement cookies are used to provide visitors with relevant ads and marketing campaigns. These cookies track visitors across websites and collect information to provide customized ads.
Others
Other uncategorized cookies are those that are being analyzed and have not been classified into a category as yet.
SAVE & ACCEPT
Powered by CookieYes Logo