Mead & Hunt provided multidisciplinary engineering and construction support services to modernize site and utility infrastructure at the Combined Support Maintenance Complex. The project improved electrical reliability and maintainability while upgrading site infrastructure to support continued facility operations.
A key component of the project was modernizing the complex’s aging electrical infrastructure. The facility was served by a combination of 240-volt single-phase, 240-volt three-phase, and 208-volt three-phase services, with existing electrical equipment ranging from more than 20 to more than 40 years old. Mead & Hunt consolidated four existing electrical services into a single utility point of service with centralized metering and replaced outdated service equipment with new switchgear, distribution equipment, and subpanels serving Buildings A, B, C, D, and F. Interior and exterior lighting systems were also upgraded as part of the overall electrical improvements.
Site improvements included reconstructing and expanding paved areas with approximately 13,300 square yards of new 7.5-inch-thick Portland cement concrete pavement, along with fencing modifications, curb and gutter, gates, pavement markings, signage, water distribution modifications, and utility relocations.
To support implementation, Mead & Hunt coordinated with the local electrical utility and jurisdictional agencies, completed site surveying and ground-penetrating radar investigations, and addressed stormwater regulatory requirements.