Skip to content
Horizontal-logo
  • 125 Years of Exceptional
  • Markets
    • Aviation
    • Cultural Resources
    • Education
    • Federal
    • Food & Beverage
    • Justice
    • Renewable Energy
    • State & Local
    • Transportation
    • Water
  • Services
    • Architecture & Interiors
    • Commissioning
    • Construction Services
    • Engineering
    • Environmental
    • Fabrication & Custom Manufacturing
    • Planning
    • Sustainability & Resilience
    • Technology & Security
  • Portfolio
  • News
  • About
    • Purpose & Values
    • Meet Our Team
    • Inclusion & Belonging
    • Corporate Responsibility
    • Locations
    • Scholarship Opportunities
    • Our History
    • Events
  • Careers
  • 125 Years of Exceptional
  • Markets
    • Aviation
    • Cultural Resources
    • Education
    • Federal
    • Food & Beverage
    • Justice
    • Renewable Energy
    • State & Local
    • Transportation
    • Water
  • Services
    • Architecture & Interiors
    • Commissioning
    • Construction Services
    • Engineering
    • Environmental
    • Fabrication & Custom Manufacturing
    • Planning
    • Sustainability & Resilience
    • Technology & Security
  • Portfolio
  • News
  • About
    • Purpose & Values
    • Meet Our Team
    • Inclusion & Belonging
    • Corporate Responsibility
    • Locations
    • Scholarship Opportunities
    • Our History
    • Events
  • Careers

A Three-Phase Approach to Hydroelectric Dam Rehabilitation

  • September 26, 2025
dam spillway with water flowing through

While hydropower facilities may not receive as much attention as newer technologies like solar and wind, America’s hydroelectric infrastructure remains a valuable resource to power our communities. The U.S. hydroelectric fleet has faithfully served its role, helping meet our energy needs for the better part of the last century.

Beyond generating power, these facilities provide flood protection, water supply, and recreational opportunities to millions of Americans. With the right strategic approach, these facilities can be cost-effectively modernized for another century of service.

Here’s how a three-phase rehabilitation strategy is helping dam operators adapt aging infrastructure to enhance performance and safety.

The Strategic Three-Phase Approach

Phase 1: Assessments Build the Foundation for Smart Decisions

Before rehabilitation work begins, an assessment is often the first step in identifying and prioritizing rehabilitation opportunities. A FERC Comprehensive Assessment (CA) identifies potential failures and develops risk information from a safety perspective to better prioritize investments. Specialized studies like Hydrologic Hazard Analysis (HHA) provide the technical foundation for understanding loading conditions used in developing Potential Failure Modes (PFMs) during the CA process.

Real-World Impact

Mead & Hunt conducted a detailed HHA for a large reservoir used for hydropower, flood protection, and recreation in the Midwest. Our detailed HHA evaluated extreme hydrologic loading conditions across dozens of upstream reservoirs. By developing inflow-duration and stage-frequency curves, plus incorporating historical flooding data, we provided dam operators with quantitative information to assess risk and make an informed decision for dam safety rehabilitation and operational planning.

Phase 2: Interim Repairs Buy Time for Strategic Solutions

When structural concerns arise from routine monitoring or unexpected failures, interim repairs can offer immediate safety improvements while permanent solutions are being developed. These targeted improvements are applicable when operators face high demolition costs, lengthy agency approvals, or require specialized studies, such as spillway erodibility analyses or Probable Maximum Flood (PMF) studies, that could delay larger repairs.

Case Study

At a California hydropower facility originally built in the mid-twentieth century, a phased interim repair program was initiated at a combined hydropower forebay and diversion dam. Instead of rushing into expensive permanent reconstruction, our team designed a phased repair program delivered over several short construction windows to minimize impact on operations.

The repairs focused on restoring structural integrity of the joints and hydraulic performance while a long-term solution was developed in coordination with a site-specific PMF study by others. Critical interim repairs included wall stabilization, joint sealing, concrete patching, apron repairs, drain inspection and clearing, and select wall drain replacement. This risk-informed approach identified repairs while balancing the construction schedule and continuing effective water management. Operations and monitoring were adjusted to accommodate the interim conditions and justify the continued use of the spillway.

Engineer oversight, combined with quality assurance testing, assured repairs met performance standards. The interim repairs have successfully extended spillway service life by over five years, providing valuable time to develop a plan for larger upgrades while maintaining safe, reliable operation.

Technical rendering of an interim spillway design
Interim spillway joint repairs with hydraulically favorable offset.

Phase 3: Permanent Improvements Reinforce Century-Old Solutions

Modern spillway design involves hydraulic innovation, structural resilience, and practical constructability to build facilities that meet current standards while improving overall performance.

Innovation in Action

A recent in-place spillway replacement project for a nearly century-old mountain hydropower facility exemplifies this approach. Assessment had identified structural deficiencies and capacity limitations in the original spillway chute, which decreased in width and turned along its length, potentially causing water to overtop onto erodible ground during higher flows.

The solution involved a curved deflector design that directs flow upward and back toward the spillway center, more than doubling flow capacity within the existing footprint while requiring significantly less wall height than a straight extension.

Technical rendering of a curved deflector that increases spillway chute capacity
Curved deflector increases spillway chute capacity.

The modernized design also includes:

  • Hydraulically favorable joint offsets to mitigate cavitation risk
  • Embedded PVC waterstops to minimize under-slab flow
  • Mechanical connections protecting against hydraulic jacking
  • Robust underdrain systems with accessible inspection and maintenance features
  • Chute slab anchorage designed for uplift protection

Construction challenges in the steep, remote location were addressed through strategic crane pad design, widened access roads, and the use of precast concrete segments for the curved deflector. This approach streamlined installation while accommodating short construction seasons and wildfire risk.

Hydroelectric Remains Viable and Valuable

After 150 years of operation, adhering to increasingly sophisticated regulations and safety requirements, America’s hydroelectric fleet has proven its resilience and adaptability. As the real-world case studies above highlight, proactive investment in strategic rehabilitation is cost-effective and a pathway to securing another century of reliable, clean energy. With innovative engineering and a strategic three-phase approach to improving aging hydroelectric infrastructure, these facilities are positioned for long-term success.

headshot of Ryan Greif

Ryan Greif, PE

Ryan is the hydrology and hydraulics engineering supervisor for Mead & Hunt’s dams, hydro, and flood risk reduction team. For 17 years, he has planned, analyzed, modeled, and designed hydroelectric facilities, assuring dam safety and providing flood protection. When he’s not perfecting a new recipe with his five favorite taste-testers, he is exploring ways he can turn his love of Excel into a full-time gig.

Linkedin Envelope Readme
PrevPrevious

Most Popular

Justin Kise Named Mead & Hunt’s Water Group Leader
September 25, 2025
Nicki Combs Named President-Elect of ACRA
September 10, 2025
A Glimpse into History: Why Jelly Juice Jars Were Found in Virginia Schoolhouses
August 26, 2025
Transportation Impact Fees: How Developer Contributions Support Healthier Communities
August 20, 2025

Main Menu

  • Home
  • Markets
  • Services
  • Portfolio
  • News
  • About
  • Careers
  • Home
  • Markets
  • Services
  • Portfolio
  • News
  • About
  • Careers

Useful Links

  • Ebids
  • Corporate Responsibility
  • Equipment & Parts
  • GSA Schedules Program
  • Government Contract Vehicles
  • Policy for Third-Party Recruiters
  • Transparency in Coverage
  • Ebids
  • Corporate Responsibility
  • Equipment & Parts
  • GSA Schedules Program
  • Government Contract Vehicles
  • Policy for Third-Party Recruiters
  • Transparency in Coverage

Get in touch

  • Apply Today
  • Contact Us
  • Locations
  • Title VI
  • Apply Today
  • Contact Us
  • Locations
  • Title VI

Connect with us

Linkedin Facebook Instagram Vimeo

© 2025 Mead & Hunt, Inc. All rights reserved.

[uc-privacysettings] | Privacy & CCPA Policy | Do Not Sell | Site Map
This website uses cookies to improve your experience. Read full privacy policy
ACCEPTREJECTSETTINGS
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Functional
Functional cookies help to perform certain functionalities like sharing the content of the website on social media platforms, collect feedbacks, and other third-party features.
Performance
Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Analytics
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics the number of visitors, bounce rate, traffic source, etc.
Advertisement
Advertisement cookies are used to provide visitors with relevant ads and marketing campaigns. These cookies track visitors across websites and collect information to provide customized ads.
Others
Other uncategorized cookies are those that are being analyzed and have not been classified into a category as yet.
SAVE & ACCEPT
Powered by CookieYes Logo